POWER SECTOR
REFORMS
By A K Basu,
Secretary,
Ministry of Power
Introduction
The Indian Power Sector
has made significant strides in the past fifty years by increasing its
installed capacity from 1,300 MWs at the time of independence to about
99560 MWs as on 30th September 2000. The size and expansion of the transmission
and distribution network has also increased substantially. There has also
been progressive inter-connection of power systems at the State level to
start with and then at the regional level. The entry of Central Public
Sector Undertakings into power generation and transmission have helped
further consolidation of the power system in the country. A National Power
Grid, which has been approved in principle by the Government, is already
on the horizon. The growth achieved almost entirely through investments
in the public sector have indeed been impressive. However, despite this
impressive growth we continue to face power shortages. In the Eighth Plan
period, we could achieve only a little above half the generation capacity
addition target we had set for ourselves. In the Ninth Plan period also
the final position may not turn out to be much better. The poor financial
health of the State Electricity Boards as also inadequate investment in
the Power Sector are largely responsible for this inability to meet targets.
Financial Performance
of SEBs.
* Most of the
State Electricity Boards are cash strapped. They are not even able to earn
a minimum Rate of Return (ROR) of 3% on their net fixed assets in service after providing
for depreciation and interest charges in accordance with Section 59 of the Electricity (Supply)
Act, 1948.
* One of the
reasons for this dismal performance is that a substantial portion of cost
remains uncovered on account of lower average tariff. While the cost of supply of electricity
has shown an increasing
trend, the tariff has not been commensurate with this, thus, widening the gap between
the average cost of supply and realisation.
*
The cumulative outstanding due from SEBs to the Central Power Sector Undertakings (CPSUs)
as on 31st October,2000 stands at a collosal Rs.26858.07 crores and have been progressively increasing. These
heavy overdues are a source of serious concern since they threaten to drag the so-far healthy
Central Power Sector Organisations into sickness as well.
Commercial performance
Revenue arrears receivable
by SEBs stood at Rs. 17235 crore during 1997-98 representing 33.8% of the
sales revenue. State and local Government offices are prominent among the
defaulters.
Need for reforms
Given the financial
health of the SEB’s, we shall very soon reach a stage of no return if we
don’t take immediate corrective measures. Our per capita power consumption
stands at only 338 unit (against over 800 units in China and over 13000
in the US) which is one of the lowest in the world. The foreseeable fall
out of our inaction can be discussed as under :-
Poor prospect of capacity
addition (Increasing Demand-supply gap)
With the existing state
of affairs, the State sector may at best add another 4,000 MW and the private
sector another 10,000 MW by 2012. The Central sector is likely to add 40,000
MW during this period. If the outstanding dues of SEBs continue to mount
as estimated, even this capacity addition by the Central sector would be
difficult. Our requirement as per the 16th Electric Power Survey (EPS)
is about 1,00,000 MW. Thus, there will be a gap of nearly 46,000 MW as
per the requirement. As a consequence, the energy shortage will widen from
the present 6% to 18% and peak shortage from 11% to 24%. This will adversely
affect the economy as a whole and put a brake on the rate of economic growth.
Financial closure
of new power projects difficult due to payment uncertainty.
It is estimated that
Rs.1,000,000 crore would be required during the Xth and XIth Plan periods
for power generation and matching transmission and distribution purposes.
The generating companies are unable to make these investments because their
plans are getting affected due to the inability of the SEBs to pay them
back. It is a vicious circle. The SEBs cannot raise revenue as they have
poor system of selling electricity and collecting revenue. Financial institutions
and foreign investors are not coming forward to finance private sector
power projects because of their assessment that such projects would not
be in a position to recover investments due to poor financial health of
SEB’s.
Dues of CPSU’s will
lead to their sickness.
The CPSU’s are getting
increasingly constrained from making new investments as their balance sheets
are getting adversely affected due to poor recoveries from the SEBs. Government,
both Central and State, cannot provide budgetary support to their corporations
owing to their own financial constraints.
Rural Electrification
-
Declining trend
About 81,600 villages
in the country are yet to be electrified. There is a steep decline in the
number of villages electrified since the Seventh Plan as in their perilous
State of finances, SEBs find rural electrification as a non-viable proposition.
Current trend indicates that Bihar will take 702 years, West Bengal 71
years, UP 26 years and Orissa 19 years to complete village electrification.
Dependence on Diesel
Non-availability and
lack of proper supply of electricity leads to increased dependence on diesel
for running pump-sets, generators etc. This in turn adversely affects the
economy.
Poor quality of power
and service
Supply of power is highly
erratic. Blackouts are on the increase. Customer service is very poor.
All this affects economic growth and the quality of life of the people.
The deteriorating situation,
if not stemmed adequately and immediately, will make the Indian economy
and industry highly uncompetitive.
Objective of and GOI
initiatives towards reforms
The objective of reforms
in Power Sector is to bring in commercial viability in the power supply
industry so as to ensure power supply on demand to all consumers at reasonable
prices. The focus of reform initiative of the Government of India has been
to
-
meet demand - supply Gap
-
supply Quality Power
-
supply power at affordable
cost
-
have a financially viable
sector
-
remove tariff distortions
-
improve operational efficiencies
- improve PLF - control losses, leakages, theft
-
give choice to the consumers
-
introduce competition
-
access new sources of finance
The Government of India
have taken a pro-active role in unleashing and accelerating the process
of reform in the power sector in the country.
In the Chief Ministers
Conference held on 3.12.1996, a Common Minimum National Action
Plan for Power (CMNPP) was adopted which inter-alia stipulated setting
up of independent State Electricity Regulatory Commission (SERC) for rationalisation
of tariff by each State / UT, privatisation of distribution system gradually,
providing maximum possible autonomy to the SEBs and to restructure and
corporatise them for running on commercial lines. The conference also resolved
that cross subsidisation between categories of consumers may be allowed
by SERCs. No sector shall, however, pay less than 50% of the average cost
of supply (cost of generation plus transmission and distribution). Tariffs
for agricultural sector will not be less than fifty paise per Kwh to be
brought to 50% of the average cost in not more than three years.
The Chief Ministers/Power
Ministers Conference held on 18.12.1998, after taking into account
the significant changes that have taken place in the power sector after
adoption of the CMNPP, decided that a new initiative needs to be taken
to move the power sector into the next phase of reforms. With this end
in view, a plan of action was adopted for implementation, which inter-alia
included constitution of State Electricity Regulatory Commissions (SERCs)
before 31.3.1999, announcement of a power sector reform policy and initiate
steps for drawing up of a reform bill in a time bound manner, corporatisation
and commercialisation of generation, transmission and distribution for
operating them on commercial principles and to undertake distribution reforms
by increasing entry of private investors, wherever feasible.
The Chief Ministers/Power
Ministers’ conference held in New Delhi in February 2000 is another
important milestone towards reforming the power sector. The conference
decided that the key elements of the reforms strategy would be:
-
Energy Audit at all levels.
-
Time-bound programme of
100% metering of all consumers by December 2001.
-
Reduction and finally,elimination
of power theft within a specified time frame.
-
Strengthening/upgradation
of sub-transmission and distribution system by taking sub-station as an
unit on a priority basis.
It was decided that if the
above was not unattainable in the existing set up, corporatisation / cooperatisation
/ privatisation of distribution would have to be undertaken.
The Electricity
Regulatory Commissions Act, 1998 has been enacted with the objective
of rationalisation of tariff, transparent policies regarding subsidies,
promotion of efficient and environment friendly policies. The Central Electricity
Regulatory Commission (CERC) was constituted in July 1998. The functions
of the CERC are to promote competition, efficiency and economy in the power
sector besides determining tariff for generating stations owned and controlled
by Central Government, other inter-state generation projects and inter-state
transmission. Since then 12 States/UTs (West Bengal, Uttar Pradesh, Tamil
Nadu, Rajasthan, Punjab, Maharashtra, Madhya Pradesh, Karnataka, Gujarat,
Delhi, Andhra Pradesh, Arunachal Pradesh) have constituted/notified constitution
of their State ERCs. Orissa and Haryana are the two States who have constituted
SERC prior to the ERC Act, 1998.
STATUS OF REFORMS
IN THE STATES
The States of Orissa,
Haryana, Andhra Pradesh, Uttar Pradesh, Karnataka, Rajasthan and Delhi
have enacted their State Electricity Reforms Acts which provide inter alia
for unbundling/corporatisation of SEBs, setting up of SERCs, etc. Madhya
Pradesh Reform Bill has been passed in the State Assembly. Government of
India has approved Gujarat Reform Bill for introduction in the State Assembly.
As many as fourteen states
(Orissa, Haryana, Andhra Pradesh, Uttar Pradesh, Karnataka, West Bengal,
Tamil Nadu, Punjab, Delhi, Gujarat, Madhya Pradesh, Arunachal Pradesh,
Maharashtra and Rajasthan) have either constituted or notified the constitution
of SERC. The Electricity Regulatory Commissions of Orissa, Andhra Pradesh,
Maharashtra, Uttar Pradesh and Gujarat have issued tariff orders.
The SEBs of Orissa, Haryana,
Andhra Pradesh, Karnataka, Uttar Pradesh and Rajasthan have been unbundled/corporatised.
Delhi Vidyut Board will be unbundled in the near future.
The reform process in
Orissa has progressed significantly with privatisation of distribution
in the state. The four subsidiary companies of GRIDCO have been disinvested
in favour of the private companies. BSES Ltd. has taken over the three
distribution zones (WESCO, NORTHCO and SOUTHCO) and the US based AES Ltd.
has taken over the Central Zone. The Power Generation Corporation (OPGC)
has also been disinvested to the extent of 49%.
The private distribution
companies have reported of reduction of T&D losses, decrease in gap
between revenue and expenditure, increase in collection and good progress
towards metering of all consumers.
GOI support to State Governments
for reforms
The Ministry of Power
has signed a Memorandum of Agreement (MOA) with the Government of Karnataka
on 12.2.2000 with the Government of Uttar Pradesh on 25.2.2000 and the
Government of Madhya Pradesh on 16.5.2000 charting out the programmes and
agreements for power sector reforms in these three States.
MOA with Government of Karnataka
The MOA with the Government
of Karnataka envisages unbundling of transmission and distribution and
privatisation of distribution by December, 2001, 100% electrification of
villages, energy audit at all levels, full support to the regulatory commission
etc. In reciprocation, the Government of India has committed support, among
other things, for reduction in T&D losses, strengthening and improving
the transmission network and enabling supply of additional power to Karnataka,
Rural Electrification Programme, Structural Adjustment, new generating
capacity and allocation of additional power from Central Generating Stations.
MOA with Government of UP
In the MOU signed with
the Government of Uttar Pradesh, the areas in which the actions are to
be taken in a time bound manner are: segregation of transmission and distribution
functions within UPPCL, energy audit, metering for all consumers, distinct
distribution profit centres with separate commercial accounts, commercial
viability in distribution failing which privatisation and support to the
State Electricity Regulatory Commission. The Government of India has agreed
to support the State Government in various ways, some of which are : renovation
and modernisation of thermal and hydro Power stations and undertaking transmission
works, reform related studies, metering of all consumers. Required financial
assistance would be provided through PFC. In addition, there would be joint
venture hydro projects between NHPC and UPJVNL, acceleration of rural electrification
through REC and additional allocation of power directly to the distribution
centres from new central sector generating stations.
MOA with Government of Madhya Pradesh
In the MOA with the
Government of Madhya Pradesh, the areas in which the actions are to be
taken in a time bound fashion are: reorganisation of MPEB, 100% electrification
of villages and hamlets, metering of all suppliers by 31.12.2001. It has
been dicided in the MOA that all classes of consumers should be made to
pay atleast 75% of the cost of supply of electricity subject of decision
of SERC regarding subvention by the State Government. The Government of
India has agreed to allocate an additional 100 MW from Central Generating
Station for the state. Powergrid and MPEB will work in enclose cooperation
for strengthening of transmission network in the state and as a recognition
of reform, Powergrid shall also invest in inter-state transmission lines.
In addition, GOI shall fully assist the State Government in raising funds
for structural adjustment, and NHPC shall be having a joint venture with
the State Government for completing the ongoing hydro power projects.
Draft Electricity Bill 2000
The Ministry of Power
has been contemplating a new legislation, which would replace the three
existing electricity laws namely, The Indian Electricity Act, 1910, The
Electricity (Supply) Act, 1948 and the Electricity Regulatory Commissions
Act, 1998. One of the primary aims of the proposed legislation is to obviate
the need for each State to legislate individually.
The Draft Bill suggests
inter-alia, corporatisation of the State Electricity Boards and their restructuring
into separate entities that would provide for accountability based on profit
centres, whether public or private. The State Electricity Boards were created
by Central legislation, viz., the Electricity (Supply) Act, 1948 and therefore
a Central legislation for transformation of this section by doing away
with the statutory requirement of State Electricity Board and providing
the legal framework for functioning on commercial lines with independent
regulation is necessary.
It is also necessary
to make it compulsory for the States to have a Regulatory Commission either
individually or jointly. Further, the Draft Bill provides for several new
features like trading, spot market, open access etc., keeping in view the
future of power sector.