NATIONAL THERMAL
POWER CORPORATION
REVISED VISION
AND CORE VALUES
By Our Correspondent
For National Thermal
Power Corporation (NTPC), it was another year of satisfying performance.
The Corporation achieved new milestones in turnover, profit and generation
of power and impressively progressed in engineering, environment management
and human resource development too.
NTPC touched a turnover
of Rs. 17184 crore during 1999-00- an increase of 19.6% over last year's
turnover of Rs. 14372 crore. The net profit after tax has increased from
Rs. 2815.73 crore during 1998-99 to Rs. 3424.53 crore in 1999-00 -- an
increase of 21.62%.
The return on capital
employed and return on networth increased from 13.37% and 14.13% in 1998-99
to 13.86% and 14.97% respectively in 1999-00.
The company improved
its ranking in Asiaweek's survey of the top 1000 companies of the Asia-Pacific
Region (including Japan). In terms of sales and profit NTPC's ranking has
improved from 344th to 299th and 40th to 31st respectively in comparison
to last year.
NTPC declared a total
dividend of Rs.650 crore for the financial year ended 1999-00, out of which
an interim dividend of Rs.300 crore has been paid.
With a total capacity
of 19435, MW, which is around 20% of total installed capacity in the country,
NTPC in the year under reference contributed 25% of all India's total generation.
The generation of power by the company has gone up to 1,18,676 Million
Units (MUs) of electricity during 1999-00.
NTPC coal stations achieve
a Plant Load Factor (PLF) of 80.4% (against a National Average PLF of 67.3%)
and availability factor of 90.06%. The combined PLF of stations at Northern,
Southern and Western Region during the year was 89.6%. However, inadequate
demand in eastern region led to continual backing down of stations and
resulted in a lower PLF of 54.3% in that region.
In 1999-00, seven stations
namely Dadri (coal), Singrauli, Ramagundam, Vindhyachal, Rihand, Korba
and Unchahar achieved a PLF of more than 85%. Dadri coal registered a PLF
of 96.1% the highest in the country.
For the period from April
to August, 2000, five NTPC stations namely Singrauli, Dadri (coal), Badarpur,
Ramagundam, and Korba are among the top ten performing stations in the
country.
As per the survey, based
on 1998 data, carried out by Datamonitor UK, NTPC is the 6th largest in
terms of thermal generation and the second most efficient in terms of capacity
utilisation amongst the top 10 utilities.
The position of receivables
continued to be an area of serious concern. The total outstanding dues
including a surcharge of Rs.4682.87 crore stood at Rs. 12791.22 crore as
on March 31,2000. The total realisation including central appropriation
was about 87% in 1999-00. The total outstanding as on August 31, 2000 is
Rs.15310.92 crore.
Central Electricity Regulatory
Commission (CERC) has notified vide order dated January 4, 2000 the implementation
of ABT for central power generating utilities. The scheme notified will
have serious implications and will hamper the capacity addition programme
of NTPC by affecting the internal resource generation.
NTPC has filed a review
petition with the CERC and also appealed to the Delhi High Court against
the Availability Based Tariff Order. The CERC has since stayed the implementation
of ABT.
The total approved investment
of NTPC as on 31.03.2000 was Rs.44703.17 crore corresponding to an approved
capacity of 22,935 MW.
The Authorised Share
Capital of NTPC remained unchanged at Rs.8000 crore during 1999-2000.
NTPC has funds committed
for over Rs. 7000 crore from various domestic Public Sector Banks and Financial
Institutions for participating in the capacity addition programme.
NTPC continued to accept
deposits from public in terms of the provisions of the Companies Act, 1956.
The total deposits, as on end March 2000, stood at Rs.325.26 crore.
During the year NTPC
has utilised Rs. 639.16 crore from external borrowings taken from various
sources. The cumulative utilisation in respect of foreign loans was Rs.
16,577.67 crore upto 31st March 2000.
NTPC remains the single
largest coal user in the Indian Power Sector with the consumption of 70.57
MTs (including Badarpur 3.53 and Balco 1.70 MT) during the year 1999-2000.
Gas supply to operating
gas stations along the HBJ line during 1999-2000 registered an increase
and gas receipt was 10.50 MCMD (excluding 1.11 MCMD for Faridabad Gas)
as compared to last year's supply of 9.96 MCMD, registering an increase
of 5.42%. However, Gandhar Project continued to suffer from inadequate
gas supply resulting in total loss of generation to the tune of 2732 MUs
which was marginally lower than previous year's 3197 MUs.
During 1999-2000, 1116
MW was commissioned ahead of schedule. This included Vindhyachal Unit VIII
(500 MW), Unchahar Unit IV (210 MW) and Faridabad gas turbines I and II
143 MW, each, all ahead of schedule. On 31.07.2000 the combined cycle (ST)
of Faridabad Gas Project (144 MW) was also commissioned ahead of schedule.
NTPC would add 3140 MW
in IX Plan (including 440 MW Tanda taken over from UP).
With a view to achieve
a capacity of 40000 MW by the year 2012, NTPC has formulated an ambitious
capacity addition programme. Projects with a capacity of 3000 MW namely,
Simhadri (2 X 500 MW) and Talcher Kaniha (4 X 500 MW) are already under
implementation. 1500 MW capacity at Ramagundam-III (3 X 500 MW) and Rihand-II
(2 X 500 MW) is under bidding stage. CEA's techno-economic clearance has
been obtained for 1980 MW (3 X 660 MW) Sipat project and action has been
initiated for procurement of main plant equipment. In addition, infrastructure
activities have been taken up for 800 MW Koldam Hydro Power Project. Feasibility
reports for four projects (namely, Kahalgaon-II, Barh, Vindhyachal-III
and Sipat-II) with a total capacity of 4960 MW have been submitted to CEA
of techno-economic clearance. Further, proposals of new projects with a
capacity of approximately 5000 MW are presently under formulation.
In addition to Koldam
project, NTPC is in the process of identifying suitable sites for setting
up/taking over hydro projects in different states.
JOINT VENTURES
UTILITY POWERTECH
LTD. (UPL)
During the year 1999-2000,
UPL has received orders for approximately Rs. 52 crore. In this year, the
company has also paid its maiden dividend @ 10% on the paid up capital.
NTPC-ABB ALSTOM POWER
SERVICES LTD. (NASL)
NTPC has formed a Joint
Venture Company with ABB KRAFTWERKE AG, under the name of "NTPC-ABB ALSTOM
POWER SERVICES LIMITED", (NASL) for taking up renovation and modernisation
assignments of Power Plant both in India and SAARC countries. The company
has started functioning and has already secured some assignments with order
value of approximately Rs.10 crore under competitive bidding.
JOINT VENTURE FOR
SETTING UP LNG BASED TERMINALS GUJARAT PIPAVAV LNG LTD.
* NTPC has signed
an MOU with Sea King infrastructure Limited, British Gas and Gujarat Pipavav
LNG Ltd. for
equity participation to the extent of 26% in the Joint Venture Company,
Gujarat
Pipavav LNG Limited
(GPLNG). GPLNG shall be developing an LNG regassification terminal at
Pipavav. The
regassified LNG is likely to serve NTPC's gas requirements for its expansion
units of 650
MW each at Kawas and Gandhar.
* PETRONET LNG LTD.
NTPC has also
signed an MOU with Petronet LNG Limited (Petronet) for acquiring 10% of
its
equity. Petronet
is presently developing LNG regassification terminal at Dahej. The
regassified LNG
from this terminal is likely to serve NTPC's gas requirements for its
expansion units
of 650 MW each at Anta and Aurayia.
CONSULTANCY SERVICES
During the year the
consultancy wing has secured 18 orders valued at Rs. 37.09 crore. The total
earnings and the net profit of the division during the year is Rs. 12.03
crore and Rs. 6.10 crore respectively.
NEW TECHNOLOGIES
Super Critical Units
With the thrust on improvement
in efficiency and introduction of environmental friendly technology, NTPC
has decided to go for super critical parameters in future. To take advantage
of economy of size, NTPC has also decided to adopt super critical 660 MW
units for future power plants in Sipat, Kahalgaon-II, North Karanpura and
Barh.
ENVIRONMENT MANAGEMENT
Till date NTPC has planted
approximately 14 million trees at its different projects. NTPC stations
have received a number of prestigious Environmental Awards and many stations
have been accredited with ISO-14001 Certification.
ASH UTILISATION
During the year 1999-2000,
27.0 lac tonnes of ash has been utilised for various productive purposes.
Feasibility study has
been done under USAID programme for haul back from Singrauli to Gorbi mines.
Ash from Badarpur Ash Pond is being used in Delhi Metro Rail Corporation
Ltd.'s project for land filling and embankment purposes.
HUMAN RESOURCE MANAGEMENT
The total strength of
employees of the corporation stands at 24024 as on 31.03.2000 as against
23630 as on 31.03.1999. The overall Man-MW ratio for the year 1999-2000
including the recently taken over Tanda Project was 1.10.
EMPLOYEE RELATIONS
Industrial Relations
scenario in NTPC was cordial and harmonious. All employees had regular
interaction with the management both, through their Associations/Unions
and also individually.
AWARDS
NTPC has been winning
the Prime Minister's prestigious Shram Awards 2000 for 15 years in succession.
Shri R P P Nair of Korba project is the second NTPC employee to win the
highest Prime Minister's Shram award-the Shram Ratna. Shri Dilip Krishnan
of Singrauli Project bagged the same award last year.
Under the Meritorious
Productivity Award Scheme of the Government of India eleven stations were
selected for better performance for the year 1997-98. Besides, nine stations
were selected for reduction in Specific oil consumption and five stations
were selected for reduction in Auxiliary power consumption for the year
1997.
Eleven NTPC stations
have received "Safety Awards" for the year 1999 from British Safety Council.
|
HIGHLIGHTS
|
Turnover
of Rs 17184 crore-an increase of 19.6% over last years turnover
Net
profit increases to Rs. 3425 crore
Return
on Capital Employed and Return on Net Worth 13.86% and 14.97% respectively
Dividend
of Rs 650 crore declared for 1999-00-an interim dividend of Rs 300 crore
paid
Pre-payment
of foreign loans results in nearly Rs 8.63 crore savings for NTPC. Another
term loan prepaid in September, 2000 resulting in a saving of Rs 6.23 crore
A
record generation of 1,18,676 Million Units at a Plant Load Factor (PLF)
of 80.4% during 1999-2000
Capacity
addition of 1116 MW ahead of schedule during financial year 1999-2000.
Faridabad
Combined Cycle (ST) 144 MW unit commissioned in July, 2000 ahead of schedule.
Capacity
addition programme of NTPC doubling its capacity to 40,000 MW by 2012 in
full swing
Funds
committed for Rs 7000 crore for capacity addition programme from domestic
banks and financial institutions
Japanese
Government pledges second tranche JBIC loan of Japanese Yen 12194 Million
(Rs. 500 crore approximately) for Simhadri Project.
Total
outstanding dues Rs 15,310 crore, including surcharge, as on August 31,2000
Identifying
suitable sites for Hydro projects
Joint
ventures for LNG terminals
Prime
Minister's Shram Ratna award for the second consecutive year to NTPC employee.
Revised
vision and core values for renewed impetus for growth
|