HOW TO MINIMIZE
TIME AND COST
OVER-RUNS OF PROJECTS
By Dr. Uddesh Kohli,
Former Chairman & Managing Director,
Power Finance Corporation
It is
a well-known fact that time and cost over-runs are widely prevalent of
public sector projects. Because of these time and cost over-runs, the output
goods and services come much later and at a higher cost. In fact, some
projects often become uneconomical due to the time and cost overrun. Moreover,
the resource requirement for the ongoing projects increases considerably,
leaving very little for new projects starts. All this adversely affects
the economic development of the country.
REASONS
FOR TIME AND COST OVER-RUNS
An Analysis of the past
experience is necessary to identify the main reasons for these time and
cost over-runs and to suggest steps for minimising these.
The main reasons for
time and cost over-runs of projects can be considered in three major groups.
-
Inadequate formulation
-
Lack of proper implementation
planning
-
Poor management of implementation
Inadequate
formulation
This group will cover
aspects such as:
-
Poor field investigations
-
Incomplete and inadequate
information
-
Bad or deliberately wrong
estimation
-
Lack of expertise and experience
-
Inadequate project analysis
-
Omission of project linkages
-
Poor appraisal and investment
decisions
In the
project formulation phase, pre-feasibility and feasibility analysis play
a significant role in investment decision making. The project concept is
to be crystallised after considerable efforts, technical studies, consultations,
inter-ministerial discussions, etc. In many projects such detailed work
is not undertaken and the project concept is not properly formulated. There
are many instances where the project concept was crystallised much after
the investment decision or the scope of technology changed or the project
designing continued side by side the execution. In some cases, consultants
were not able to give proper technical details and their Geological data
needed for mining or hydel projects was not, sometimes, properly collected,
as it involved a lot of time, expenditure and effort. Experience shows
that such poorly formulated projects generally face more time and cost
over-runs.
The poor formulation
may be due to
-
lack of expertise &
experience or
-
hurry for going ahead without
spending enough time on investigations, data collection and project preparation
or
-
a deliberate attempt to
get the project approved by under-estimating costs (and/or over-estimating
benefits).
Often,
some of the weaknesses are identified during appraisal and the project
concept gets improved during this exercise but considering the short time
available for actual appraisal, inadequate data base and limited availability
of skilled inadequacies in formulation continue. In some projects, which
are not subjected to rigorous project appraisal, the weaknesses in formulation
do not get identified. Obviously, if the basic parameters of the project
are wrong, the time and cost over-runs are in-built from the very start
and these are bound to show up later.
Lack
of proper implementation planning
After the investment
decision is taken (and in many cases, even while appraisal is underway)
but before actual implementation starts, it is necessary to undertake detailed
implementation planning covering aspects such as:
-
Physical work (activities,
quantities)
-
Time plan
-
Input resources - manpower,
materials construction equipment utilities, funds
-
Inter-linkages
-
Organisation and management
systems
-
Output generation - raw
materials, manpower and utilities for operation
-
Cost planning.
Experience
shows that the majority of projects which failed on their time and cost
targets, suffered from inadequate implementation planning. Some of the
weaknesses observed are:
-
Inadequate time-plan - Some
activities either are not conceived or insufficient time is provided. For
example, land acquisition, clearances, tender evaluation, recruitment,
administrative procedures etc. are not adequately provided for in many
project time plans. In some cases incomplete or mere superficial use of
PERT/CPM techniques does not give a realistic time plan. Often the master
network is not further broken down to detailed networks for operational
levels.
-
Inadequate resource plan
and its linkage with time plan - The time plan is not matched with resources.
The implicit resource requirements (manpower, materials, money etc.) for
each period (month/quarter/year) may not meet the availability constraint
and hence the time plan may not be implementable.
-
Inadequate equipment supply
and contract planning - Individual equipment supply and other constraints
may not be matched with the network time-plan. Apart from sufficient delivery
times, in sequence deliveries may not have been determined.
-
Inter-linkages not anticipated
- Some inter-linkages (e.g. for supply of inputs, transportation, power
and other infrastructure) may not have been anticipated at all or inadequately
provided, or a dialogue with interlinked agencies not undertaken in the
planning stage with a result that the time duration for inter-linked activities
is provided unrealistically.
-
Poor organisational and
systems planning - The organisation and management systems needed for successful
implementation are not properly planned in many projects.
The manpower
development and training so as to generate necessary skills, attitude and
or organisation culture is overlooked, responsibilities for the project,
its components and activities are not specifically identified, implementation
and monitoring system which would help ensure effective execution and control,
are not developed and interface with government agencies is not adequately
provided for.
-
Inadequate output generation
planning - For generation of output goods and services, the planning for
manpower, raw materials, utilities (power, water, transport, etc.) is often
not fully carried out. Similarly, planning is needed for reaching the output
to consumers or beneficiaries. Some of these aspects might be considered
under inter-linkages but in many cases, advance market effort (both for
procurement of inputs and for supply of outputs) may have to be planned.
There are examples of projects lying physically completed but not commissioned
(and not generating outputs) for want of inputs or arrangements for supply
of outputs.
-
Poor cost-planning - Even
where project time is properly planned, the cost planning, particularly
by detailed activities, is hardly undertaken, with the result that in spite
of meeting the time-schedule, there is cost over-run (over and above what
is arising purely due to price escalation).
Poor
management of implementation
After detailed implementation
planning, the effectiveness of project management lies in execution in
accordance with the implementation plan, overcoming the problems coming
in the way by necessary corrective action. The problem areas generally
include:
-
Delays - actual activity
time more than that estimated (e.g. in land acquisition, approvals, clearances
from various agencies, design and engineering, civil works, equipment supply,
etc.)
-
Changes in scope, location,
technology, etc.
-
Law and order, labour problems
-
Failure of inter-linked
agencies
-
Unforeseeable problems such
as natural calamities, excessive rains, draughts.
Delays:
If the actual time taken for a critical activity is more than what was
realistically estimated in the implementation plan, it may result in delay
in the project completion and cost over-run. If the activity is not critical
and delay is within the float or slack available, it may not lead to time
over-run but may result into cost over-run. Typical activities where such
delays take place, have been listed above. These delays can be divided
into two groups:
-
Interauthorities (including
administrative ministries), and
-
External - those which are
outside their control and are caused by outside agencies. While the first
category directly highlights the poor management performance, the second
category indirectly reflects the management weakness, as it is their responsibility
to inter-act with the external agencies, identify and anticipate the problems
in advance and take up the problems at appropriate levels in order to overcome
them. The performance of contractors and suppliers is generally covered
by first category as the project authorities supervise their performance.
Often the incentive and penalty measures are too meagre or ineffective
to ensure on-schedule or before-schedule performance. In many cases longer
than estimated time is required due to inexperience or where technology
is to be indigenously developed and consequently greater time is needed
for learning and experimentation (e.g. in atomic energy, underground railway,
difficult underground mining projects).
Changes
in scope, location, technology - While, as stated earlier, some of
changes in scope and technology are avoidable by better investigation and
planning in the formulation stage, in many cases there may be unforeseeable
geological and ground conditions (e.g. in mining, hydel projects), sudden
changes in technology, demand, market etc., requiring changes in scope.
Many a time, when the project execution is prolonged and there is a change
of personnel, new thinking and ideas may lead to changes in scope. In most
of the cases, change in scope requires further design and engineering,
new equipment etc. and there is a consequent delay and cost over-run.
Law
and order, labour problems - Law and order problems such as civil disturbances,
labour strikes, etc. may sometimes, hamper the progress of the project
execution.
Failure
of inter-linked agencies - In most projects, unless the activities
of inter-linked agencies are completed in time, either the execution of
project work gets held up or its commissioning is delayed. These activities,
which may involve completion of respective projects by the inter-linked
agencies, include supply of power, water, building of transmission line,
road, rail line/siding; project to supply raw materials (e.g. coal, ore
or minerals), forest and agriculture produce; projects such as command
area development, housing, etc. Often there is considerable delay in the
approval of these inter-linked projects or in allocation of funds to them
in their respective budgets. In many other cases, there may be delay in
their implementation for various reasons.
Unforseeable
problems such as natural calamities - Earthquakes, cyclones, heavy
rains, floods, draughts, wars, accidents, etc. are examples of natural
calamities and unforeseeable problems which can result in delays and cost
over- runs.
HOW
TO MINIMISE TIME AND COST OVER-RUNS
The foregoing analysis
of the reasons for time and cost over-runs provides clues for remedial
steps. These can be listed as follows:
-
Better formulation and appraisal
of projects - Investment decision on a project should be undertaken only
after full investigation, collection of data, analysis and cristallisation
of the concept. Since in many projects, this analysis may be expensive
and may require preparation of the detailed project report, the first stage
clearance should be used to eliminate those project ideas which are prima-facie
not viable and on which expenses for detailed analysis may not be incurred.
The appraisal system also needs to be made more effective for checking
the data, questioning under-estimates and unrealistic assumptions. For
this purpose, suitable databank for project analysis containing data about
other similar projects (past and present) should be developed. Evaluation
studies of completed projects should also help in developing this data
bank. Once final investment decision after sound appraisal is taken, no
significant change in project concept, location, technology and scope should
normally be permitted.
-
Sound implementation planning
- Sound implementation planning is a pre-requisite for effective implementation.
Realistic, resource - based (resource requirements matched with availability
constraints) implementable plans can be formulated by using techniques
such as PERT/CPM and estimating activity times, linkages and resource requirements
realistically through an inter-disciplinary group-process where experiences
of many persons is pooled together. Here also a data bank on similar projects
(past and present) would be useful. Where project authorities do not have
sufficient experience or data, consultants can be employed for this task.
Generally, a slack of about 10-15% should be kept in reserve and an “internal
network” for shorter duration may be drawn up which may be used by the
implementing staff. Alternatively, the 10-15% slack may be implicitly included
in the time duration of the last one or two activities. This ‘reserve’
is means to meet the contingency of unforseeable or uncontrollable delays.
Good computer software packages are available for project planning with
PERT/CPM, equipment scheduling, manpower planning, cost optimisation and
control, monitoring etc., which could be effectively used. With sound implementation
planning after proper project formulation more than half of the battle
is won.
-
Advance action - After the
first stage examination and clearance when prima-facie desirability or
viability has been established, advance action on following activities
by project authorities should be permitted:
-
Acquisition of land
-
Getting essential clearance
e.g. environment, foreign investment etc.
-
Identification and type
up with main technology consultant
-
Preliminary design and engineering
-
Calling of tenders for main
long lead plants and equipments
-
Identification and positioning
of core project management team
-
Arrangement for preliminary
infrastructure facilities for construction (e.g. power, water, roads, etc.).
Some of
these advance action areas may require small investment. In the unlikely
event of the project not being finally approved for investment, only a
part of this small investment may become infructious - On the other hand,
in the likely event of the project being approved, there will be considerable
saving in time and cost.
Clearances
- Even after the government approval of the project, there may be many
clearances required from various government agencies. In order to save
time, there may be one or more ‘Empowered Committees’, consisting of the
secretaries or senior officials from concerned ministries, which may give
some of the necessary clearances. Some major projects, for which such committees
were constituted, were successful in minimising time and cost over-runs.
To start with, such committees may cover projects costing over Rs.100 crores.
Inter-linked
Projects - All inter-linked activities/projects of other agencies,
on which the completion or commissioning of this project (say XYZ) under
focus depends and which are to be undertaken primarily for the project
XYZ, should be considered, appraised and cleared together with this project
(XYZ). Where, some time gap is inevitable, it should be kept to minimum,
not exceeding 6 months. The fund allocation should also be considered and
decided at the same time. Preferably, all these funds should also be allocated
to the project XYZ in its budget (as is generally done for railway sidings)
and these should be released by the project XYZ to the agencies concerned
for the inter-linked activities/projects on the basis of their implementation
plans and progress. This will help in ensuring effective control of project
XYZ on their execution. Even where exception to this procedure is necessary
(e.g. where the inter-linked activity is a part of an integrated project
of the other agency), the fund allocation should be considered for the
inter-linked activity at the same time as the project XYZ.
Equipment
procurement and tendering - For effective coordination, the number
of contract packages should be minimum. Turnkey contracts have obvious
advantages. But adequate content of indigenous equipment and other services
has to be ensured. There has to be a marriage of the objective of the use
of indigenous equipment with the objective of minimising time and cost
over-runs. If most contracts were awarded on the basis of global tenders
to foreign contractors (assuming that they could supply and construct with
lesser time, cost and quality defects), then there would be not only under
utilisation of indigenous capacity (hence higher economic costs) but also
considerable outgo of foreign exchange and acute balance of payments problems
for the country. A better approach may be to have global tendering but
with a higher weightage (in line with the current premium on foreign exchange
considered for economic analysis on indigenous supply). But when there
is a slump in the international market even this weightage may not be enough
to ensure desired indigenisation and it may need to be reviewed. In any
case, the efficiency of indigenous equipment suppliers has to be improved.
Better
contract management, penalties and incentives - Since in majority of
projects, execution is through contracts, their proper management is a
key to minimise time and cost over-runs. The contract planning (both for
works and equipment supplies) has to be linked closely to resource-based
implementation planning of the projects. Contractors and suppliers should
be bound to give their resource and time plans integrated with project
plans (based on PERT/CPM) and follow them. Each contract’s dates should
be as per the detailed network. There should be close follow-up and interaction.
Existing penalties and incentives need to be considerably enhanced so that
contractors are also interested in on-time performance. Where delays are
anticipated, project authorities should be able to off-load contracts (partially
or fully) to other parties (either within the country or abroad) well in
time. Target cost contracts with incentives for savings should be encouraged
to minimise time over-runs. Where consultants are use for planning, awarding
and following up the contracts, the effectiveness of consultants in contract
management should be properly evaluated. ‘Expeditors’ from project authorities
or consultants can be helpful in watching progress, expediting deliveries
and giving advance warnings, as they will be stationed at or visiting the
suppliers’ shops. Contractors should be considered as partners in project
execution and help should be provided in solving their genuine problems,
as otherwise project execution will be help up.
Monitoring
- A simple and effective monitoring system is essential to identify and
anticipate the deviations from implementation plan, analyse the underlying
problem areas and suggest corrective action. Anticipation is important
from the point of view of preventing or overcoming the problems before
they occur or taking alternative steps to minimise their impact on project
time and cost. A good data bank on implementation of activities of this
and other similar projects (past and present) could greatly help in the
monitoring process. Over-monitoring should be avoided as it leads to unnecessary
paper work, tying up of project manpower resources and viewing of monitoring
as an end in itself rather than as means to achieving the ends. Emergence
of project monitoring, as a specialised profession should be encouraged.
The objective of external agencies, which are monitoring the performance,
should also be to provide help in solving problems rather than finding
faults. Joint ‘Monitoring groups’ can be established under the auspices
of the Ministry of Programme Implementation, which may consist of representatives
of the project as well as inter-linked agencies and the ministries concerned.
The groups could monitor and review the progress of the complete system
- the project and the inter-linked activities/projects. For problem solving
and action, the primary agency is the project authority. Where government
action is needed, the main responsibility lies with the administrative
ministry. For inter-ministerial problems, the ministry may seek the help
of bodies such as Ministry of Programme Implementation, which could play
a positive, coordinating role, Planning Commission, Cabinet Secretary (Chief
Secretary in the case of State Government), committee of secretaries and
cabinet committee.
Management
techniques, systems, incentives - Industrial engineering and management
techniques such as method study, value engineering, etc., can help in reducing
time duration of activities and giving up of unnecessary items/activities.
Over-specification can be avoided so that the costs can be reduced. The
project organisation should be distinct, separate from operation side,
complete with all functions, under the charge of one competent project
leader and with all responsibilities clearly defined. There should be full
delegation to project leader and his team and down the line. The systems
and methods should be clearly laid down and manualised. Human side of project
management is an important (if not more) as the quantitative techniques
and attention to inter-personal skills, interaction, human resources development
etc. is important from the very initial stage. After all, implementation
of a project is a group or team effort. It is the effectiveness of this
team effort, which will determine the success of the project. The consciousness
to adhere to time and cost schedules is to be generated at all levels.
In the projects which were successful in meeting their time cost targets,
the core project management team, starting from the top person, had full
commitment and made it a mission or a goal to complete the project within
its time schedule/cost, whatever may be problems and they achieved this.
This spirit should also be followed up with incentives (in the form of
rewards, promotions, recognitions etc.) for those who achieve time and
cost targets and punishment for those who fail badly, and this linkage
between project performance and incentives/punishment should be clearly
visible. The core project team should be properly chosen and placed preferably
during the formulation stage and thereafter it should stay till the completion
of the project. Changes in the team, particularly, the project leader,
should be made only in exceptional cases.
Assurance
of funds resources - Once a project is approved for investment and
‘go ahead’ is given, funds should be committed to meet the requirements
(both for the project and for the inter-linked activities/projects of other
agencies on which it is dependent) as determined from the programme of
work projected by resource-based network. There should not be piecemeal
or adhoc based network. It may be advisable to determine year-wise requirement
of funds for all projects under implementation for the whole plan period,
which may be updated at each annual plan. Similarly, year-wise requirements
for key materials like cement; steel can also be worked out in advance
which should be committed by the respective allocating agencies, till the
completion of the project.
Conclusion
Projects can be completed
within the realistic estimates of time and cost (except for genuine price
rise as project estimate are approved on constant base price, without provision
for escalation). The fact that some projects have been completed without
any time/cost over-runs/ in the same environment and government systems
reflects on the differential quality of project management. Case studies
on these successful projects, including a brief analysis of the systems
used by them effectively, should be widely disseminated. A large-scale
training effort should support various steps mentioned here. Implementation
of a project requires effective partnership between various agencies-project
personnel; government agencies, consultants, contractors, suppliers etc.
and all of them have joint responsibility for ensuring successful of the
project.
|