UNDERGROUND
MINE MECHANISATION PROSPECTS
AND CONSTRAINTS
By G K Jha, Chairman
& managing Director, South Eastern Coalfields Limited
Coal
is the most abundant fuel resource in India and it meets over 60% of total
commercial energy requirement of the country. Since nationalization of
the Coal Industry, it has shown a phenomenal growth and so far has met
the requirement of the country. But this growth is only on account of open
cast mining. Stagnation in U/G production continues to be a concern and
worry for quite a number of reasons:
-
UG mines produce better
quality of coal, demand for which is rising.
-
Profit generation by O/C
mines is being eaten away by the large number of loss making U/G mines.
-
Reserve of open castable
deposit is fast depleting.
Over and above, economic
liberalization and consequent reduction of import duty on coal has thrown
a new challenge to the Indian coal industry to remain competitive with
imported coal. To meet this challenge, India can no longer rely on open
cast mining alone but now has to improve production and productivity of
its U/G mines to make them efficient and economically viable.
Reasons of stagnation
of U/G production may be
-
Inadequate investment in
U/G mining because of easily available option of open cast mining and therefore
technology up gradation in U/G mines so far has been very marginal.
A large chunk of U/G production
still comes from conventional Bord and Pillar mining using drilling, blasting,
manual loading on to tubs, supporting by timbers, transportation of tubes
by series of rope haulages. In eighties, steps were taken to mechanise
various operations by introducing intermediate technology comprising of
use of Side discharge loader/Load Hauler Dumper, roof Bolting as support
system and transportation of Coal by Chain Conveyers. This intermediate
technology could not only reduce/eliminate human drudgery of basket loading
but also it could arrest the declining trend of U/G production, productivity
and improved safety and economics also.
But this plagued with
many weakness such as:
-
Productivity is unable to
match with ever increasing wages cost.
-
Sub-operations being inter-linked
i.e., cyclic in nature, it is not conducive to very high production.
-
Moreover, continuance of
use of explosive as means of coal getting remains a source of danger.
-
Large number of work persons
is required to be engaged at working faces.
-
Roof bolting by use of hand
held electric drilling is very cumbersome and slow.
-
Recovery of coal, i.e.,
percentage of extraction is not very high.
However it can be concluded
that intermediate technology has served its purpose and in order to achieve
very high production and productivity safely and with high percentage recovery
of coal from U/G mines it has become imperative to adopt modern technology
which eliminates blasting, ensures immediate support of the working face
and envisages non-cyclic operation.
The most promising amongst
the technologies are Powered support Longwall, Bord and Pillar mining with
Continuous miner–shuttle car combination, Short wall Method for extraction
of developed Pillar etc. Powered support Longwall Technology contribute
nearly 50% of the global production of coal from Underground mines and
is thus most prevalent in leading coal producing countries all over the
world. In India also this technology was introduced in eighties.
Powered Support Longwall
faces in India barring few exceptions have not been able to give desired
level of production due to long selection of equipment, for want of adequate
geo-technical information, in adequate knowledge about assessment of support
requirement, inadequate infrastructural capacity like transport, ventilation,
power supply, non availability of spares etc. But the experiences gained
the operation of the faces are very valuable and should not be allow to
go waste. Every country faced such failures in the initial stage.
So, SECL went ahead
to introduce this technology in 3 U/G mines namely Balarampur, New-Kumda
and Rajendra. Performance of these 3 Long Wall faces is quite encouraging,
each face producing more than 2000 T/OMS on average is as high as 3.0.
Singareni Collieries are operating six Powered support Longwall faces with
fare degree of success. There is no doubt about immense possibilities of
this technology of applied in Suitable locales after through geo-technical
investigations.
Strata control problem
in Indian Longwall faces are mostly because of difficult caving characteristics
of the overlying strata. Possibilities of including caving by blasting
the goaf should be seriously explored. At shallow depth, problem of caving
could be solved in SECL PSLW projects by goaf blasting drilled from surface.
This should be considered as major break through. Also in Bord and Pillar
mining with massive stand stone roof induced caving of the roof has been
successfully carried out by long hole blasting in the goaf from underground
itself. Similarly for Powered Support Longwall faces as greater depth,
long hole goaf blasting from underground can also be tried. If this is
successful, major battle is own. One such proposal has already been mooted
for hard roof management at Churcha UG mine awaiting green signal from
DGMS.
The most widely practiced
method of mining in India is Bord and Pillar mining. B&P method of
mining can also be fully mechanized by using Continuous Miner-shuttle car
combination and Mechanised roof Bolter.
South Eastern Coalfields
has already taken action for introduction of this technology in some of
its U/G mines and expected to be operative in 2001.
A large quantum of coal
is locked in developed pillars all over the country. If high production
and productivity is to be achieved in extraction of these developed pillars,
Short Longwall needs to be tried at SECL one such proposal
is already on the anvil.
Earlier high technology
area did not meet with desired level of success because of, as I earlier
said, wrong selection of equipment, inadequate geo-technical information,
lack of knowledge regarding strata control etc. and last but not the least
the equipment supplier having no stake in success of technology.
Now SECL has entered
into agreement with some of the equipment suppliers for supplying equipment
on joint risk and gain sharing basis. In this agreement 50% of the equipment
cost will be paid in installments and balance 50% will be paid on the basis
of per tonne of production achieved. Maintenance cost also
will be paid on the basis of per tonne production. This will involve the
equipment supplier in the entire production process, thereby eliminating
the chance of wrong selection of equipment or wrong methodology of applying
the technology. These suppliers of equipment will provide credit package
from overseas bank for procurement of equipment.
Application of high technology
like PSLW, Continuous miner in large number of U/G mines will need
huge capital investment and these may not be possible over night. In the
meantime various operation like roof bolting, Coal getting etc. can befurther
mechanised as an intermediate step.
Roof bolting operation
can be mechanised by using portable hydraulic roof bolter mounted
on or connected to side discharge loader. Or alternatively mobile hydraulic
roof bolter can be developed making use of old SDL. Use of mobile drilling
machine in place of hand held drill may also prove worthwhile.
Support of green zone
area in Bord and Pillar development need to be re-looked. To prevent bed
separation immediately after exposure, grouting with resin capsule instead
of cement capsule should be thought of. It can be cost effective if small
dia holes are drilled by using smaller dia drill bits and drill rods.
Lower capacity continuous
miner with smaller capacity coal hauler can be tried. One road header has
been converted to Continuous miner mode and is being used successfully
in one of the SECL U/G mines. Seeing the success of this converted Continuous
miner, 3 more Road headers are being converted for use in different mines.
This technology needs quite modest investment almost equivalent to investment
in SDL district, but district OMS achieved is much higher compared to SDL.
Wages cost constitutes
nearly 50% or more of total cost of production. Rising trend of wages and
salaries has got a substantial impact on the production cost. In order
to minimise this impact, we do not have any alternative other than modernaisation
our underground mines any longer.
To make the modern
technologies a success story in India, we must learn from our past mistakes
so,
-
We must select proper equipment.
For this, we should try to involve the equipment suppliers in the production
process.
-
We must plan our mines very
meticulously with proper provision of infrastructural facilities
like proper system of coal evacuation, ventilation, power supply etc.
-
We must develop and expand
proper knowledge base regarding strata control etc. Our Research
Institute, Premier Educational Institutes should come forwards towards
this direction and have more interactions with the field engineers to keep
themselves abreast of the industry’s need.
-
We must try to indegenise
the manufacture of the equipment and spares.
-
Develop human resource compatible
with the technologies.
If we do all these, I firmly
believe that the technologies, which have proved to be highly successful
all over, the world, will succeed in India also.