|
Issues In Hydro Power Development
By V.S Bisht, Senior Manager
& G. S. Patra, Senior Manager
Power Finance Corporation Ltd, New
Delhi
Introduction
Hydro power in
one form or other is one of the oldest energy sources servicing the human
civilization. The new environmental laws affected by the danger of global
warming have made energy from hydro more relevant than ever. Depletion
of fossil fuel and their rising prices have compelled the planners to have
a fresh look on power from hydro. For a developing economy like ours, where
major energy needs are met by importing petroleum products, resulting in
outgo of precious foreign exchange, the role of hydropower assumes much
greater importance.
The hydropower projects have some
specific advantages, which make them attractive for the balanced development
of the power sector. Flexibility in operations (quick start and stopping,
load acceptance and rejection) and suitability for meeting the peak demand
thereby enhancing the system reliability has made hydropower a preferred
mode of energy generation.
Hydro Development- Present
Status
Our country is
endowed with enormous potential of hydropower generation. However, the
actual pace of development has been below the desired level. As per the
studies carried out by CEA the economically exploitable hydro potential
from major/medium schemes in the country has been assessed as 84,044 MW
at 60% load factor, corresponding to an approximate installed capacity
of 1,50,000 MW. As on 31.3.2002, only 14,176 MW of hydro potential has
been developed and nearly 5169 MW is under development. Thus, a large amount
of hydro potential (nearly 77%) is yet to be tapped.
Adverse Hydro-Thermal mix -
A cause for concern
The slow pace of
hydropower development has resulted in a poor hydrothermal mix. In the
absence of adequate hydropower capacity, thermal power plants are forced
to perform the role of peaking power plants. This results in poor utilization
of thermal power plants leading to increase in the cost of generation.
In an ideal condition, for economic and stable operation it is desirable
to have thermal (including nuclear) power plants to meet the base load
and hydro power plants to meet the peak power demand. A minimum hydrothermal
mix of 40:60 has been indicated for Indian conditions to meet the electricity
demand in the most optimal manner. However, in our system the share of
hydro power which was 37% in 1947 and rose to 50% in 1962-63, now stands
at a poor 24%.
Accelerating Development of
hydro power-Policy Measures
Alarmed over the
declining ratio of hydro share in the power system, GoI was forced to tackle
problem on a war footing. A policy on hydropower development was formulated
in 1998 to accelerate the development of hydro potential. The policy among
other aspects accepted the fact of poor response of private sector and
the need to strengthen the CPSUs & SEBs for taking up new hydro projects.
Accordingly, GoI has taken several steps to accelerate capacity addition
from hydro power plants, which include the following:
-
Higher budgetary allocation for hydro
sector.
-
Investment approval of new hydroelectric
projects.
-
Identification of new projects in the
central sector for advanced action.
-
Promoting state sector projects in which
were languishing or could not progress due to inter state disputes.
-
Simplification of proceedings for transfer
of clearance.
-
Developing basin wise policy for accelerating
hydropower development.
-
Initiating basin wise ranking study
by CEA, with a view to identify those projects, which could be taken up
first so that hydropower is developed in an appropriate sequence.
-
Advance preparation of DPRs for having
shelf of potential projects ready to be taken up when the need so rises.
-
Charging of cess on electricity for
creating a fund for development of hydropower.
Keeping in view the
imperative need for development of hydropower potential, Govt. of India
has included the development of hydropower as a thrust area in the Electricity
Bill 2001, which is likely to be introduced shortly.
Hydro Power-Investment Needs
CEA’s vision paper
(Mar’2001) for development of hydro electric potential have envisaged the
following additional capacity programme in the hydro sector to meet the
growing power needs of the country economically and to improve upon the
hydro thermal mix.
Additional Capacity Programme
in the Hydro Sector
|
Plan Period
|
Hydro Capacity Envisaged
to be added (MW)
|
Likely Requirements
of Funds* (Rs. Cr.)
|
2002-07 (Xth)
2007-12 (XIth)
2012-17 (XIIth)
|
10,432
21,288
23,000
|
46,944
95,796
1,03,500
|
* - @ Rs.4.5 crores
per MW
The funds requirement
at a conservative estimate for the X Plan period (2002-07) for putting
up of nearly 10,432 MW of hydro power to the grid comes out to nearly Rs.47000
crores @ Rs. 4.5 crores per MW i.e. approximately Rs.10000 crores per year
of the plan period. This is a huge investment from any yardstick, more
so as huge investment would also be required for setting up thermal power
plants and matching transmission and distribution network.
Issues involved in hydro power
development
Major issues involved
in the development of hydropower projects are:
Long gestation period:
The gestation period of hydro power project normally comes to 6-8 years,
on an average. However, major hydropower projects can take as long as 12-15
years to complete.
Inadequate infrastructure:
Hydropower projects are generally located at remote areas. It takes considerable
time and money in providing infrastructure facilities like roads, bridges,
colony etc. Projects located in hilly areas and North - Eastern region
generally fall in this category. The time consumed in providing the infrastructure
facility may go up to many and may load the cost estimate to as much as
10 to 15%. However, the gestation period after development of infrastructure
may be 4 to 5 years only.
Land acquisition problems:
Land acquisition is the first step towards project implementation and also
an indication of the seriousness of the executing agency. The problems
arising in acquisition of land may delay the starting of construction work
and in extensive cases delay the project implementation by many years.
Environment and forest issues:
Environment and forest has become one of the major issues, which have come
in the way of speedy development of hydropower projects. The implementation
of hydropower project is getting delayed for want of environment and forest
clearance. There is a need to strike a balance between the development
and the environment.
Rehabilitation & Resettlement
issues: Connected with the issue of environment is the issue of
Rehabilitation & Resettlement (R&R) of the ousters. There are number
of projects where the progress of works has been severally hampered due
to R&R issues. Moreover, the compensation and the facilities to be
provided for R&R of outers is increasing the capital cost to a great
extent.
Inter-state issues:
Water is a state issue and thus a project on a river flows through more
than one state invariably involves resolving of inter-state issues. These
issues are best resolved by political will, off course, assisted by awards
from Tribunals on water sharing. However, a lot of time is taken in resolving
these issues, due to which the implementation of the project suffers.
Geological surprises: Himalayas,
where India’s major share of hydro potential is located are the youngest
of all the geological formations and therefore are also having one of the
most fragile ecology in the world. Although, detailed investigation regarding
geological conditions of the strata is carried out before the project implementation,
which takes lot of time, the probability of occurrence of geological surprises
cannot be completely eliminated. Depending upon the gravity of the geological
surprise like collapsing of tunnel, fault zones, cavity formation and emission
of dangerous gases, the implementation of the project can get delayed to
a large extent, besides increasing the capital cost of the project.
Law & order problem:
Poor law and order, is also one of the reasons contributing to the delay
in the implementation of the hydro project, as these are located in remote
areas where it is difficult to provide adequate security. In the North-Eastern
region many of the
Power projects get delayed due to
law & order problem.
Funds constraints:
Some of the projects are delayed due to paucity of funds as they are initiated
without proper financial closure. Shortage of funds results in slow progress
leading to time overrun, which leads to cost overrun due to inflationary
pressure, aggravating the funds problem further. The projects get caught
in a vicious circle of time & cost overrun.
PFC’s contribution in Hydro
Power Development
PFC realizes the
importance of developing hydropower and has therefore placed it as one
of the thrust area of its operation. PFC also sanctions grant for Renovation
& up rating studies of existing hydro power plants and concessional
loans for project preparation for new hydro projects. As on Mar’ 02 PFC
have sanctioned Rs. 7249 crores for hydro generation (81nos.) and R&U
(64nos.) schemes which is nearly 21.22% of the total sanction of Rs. 34,154
crores.
PFC offer financial support for
hydro power projects at a very attractive terms & conditions which
are as follows:
-
Moratorium on capital repayment up to
commissioning.
-
Long tenure of up to 10 years for capital
repayment after commissioning of the units.
-
Loan up to 70% of the completion cost.
Further assistance of 15% can also be availed for non-fund based activities
like Deferred Payment Guarantee. Thus, the fund based and non-fund based
financing can go up to 85% of the completion cost. In case of reforming
states the fund based funding can go up to 80% of the project cost.
-
For some state sector projects PEC’s
interest rate for hydropower project is less by 0.5% than the interest
rate charged for thermal power projects.
PFC’s financial support
has been extremely helpful in expediting the commissioning of many hydropower
projects, which were at the advance stage of the project, however the utility
was not able to expedite it due to constraints of funds.
Conclusion
Despite India being
endowed with large hydro potential, hydro share in the installed capacity
has fallen down to 25% as against the desired ideal hydrothermal mix of
40:60 for economical operation of the power system. Drastic efforts by
GoI for development of hydropower are yet to show positive result. Efforts
by GoI to rope in private sector has also not fruitified, in view of the
inherent risk involved in the hydro power projects like long gestation
period, R&R problem, geological surprises, problems in land acquisition
etc.
PFC's financial support has
been extremely helpful in expediting the commissioning of many
hydro power projects which were
at the advance stage of the project, however the utility was
not able to expedite it due to constraints
of funds.
Keeping in view
the large investment requirement to the tune of around Rs. 10,000 to 15,000
crores per year for addition of new hydro capacity in the X plan, increased
participation from Central and State Govt. would be required. Infrastructure
development and survey & investigation for large hydro power project
should be carried out by govt. agencies and only when the project is ready
to take off, the private sector should be invited to participate either
as a purely private company or through a joint sector venture with state
sector.
Hydro power project being capital
intensive require specialised debts of longer tenure say of
15-20 years, to avoid loading the
tariff upfront. Thus, there is a need to look into
hydro power development as a basic
infrastructure development requiring special attention
Experience in PFC
indicates that fund constraint is not the only factor coming in the way
of development of hydropower. Complexities involved in construction of
hydropower project play a far greater role in delaying the development
of hydropower. The recent policy measures adopted by GoI with regard to
speedy development of hydropower is a step towards accelerating capacity
addition of hydro power plant. Power Finance Corporation on its part has
kept the development of hydropower as one of its thrust area by providing
preferential treatment to help speedy development of hydropower. However,
more still need to be done. Debt of longer tenure for hydropower project
is one amongst them. Hydro power project being capital intensive require
specialized debts of longer tenure say of 15-20 years, to avoid loading
the tariff upfront. Thus, there is a need to look into hydropower development
as a basic infrastructure development requiring special attention.
The
authors are Senior Managers
Power Finance Corporation Limited,
New Delhi
|